Payments Training Hub
FieldMeaningRequired
:20:A unique reference assigned by the sending bank to identify this payment through its whole life. It must not repeat for the same sender within the same businessM
:23B:A four character code that tells the receiving bank how to handle the transfer. CRED means a normal credit transfer, SPAY means a SWIFT payment, SSTD means a stM
:32A:The value date on which funds become available to the beneficiary, the three letter ISO currency code and the amount to be paid. For USD 25,000 on 5 November 20M
:33B:The currency and amount in which the ordering customer instructed the payment, when that differs from the settlement currency in field 32A. It preserves the oriO
:50a:The customer who ordered the payment, identified by account number and name and address. Option K gives account, name and address in free text. Option F gives sM
:52a:The financial institution that ordered the transfer when it is not the sender of the message. It is normally the bank holding the ordering customer account in aO
:53a:The account held by the sender with the receiver, or the correspondent bank through which settlement will occur. It tells the receiving bank where to debit the O
:54a:The account held by the receiver with another bank, used when the receiver does not hold the sender account directly. It identifies the next bank in the settlemO
:57a:The bank where the beneficiary holds an account, when it is not the receiver of the MT103. It directs the receiving bank to forward the payment to the correct aO
:59a:The final recipient of the funds, identified by account number and name and address. Option A gives the account and BIC, option F gives structured name and addrM
:70:Free text information for the beneficiary explaining what the payment is for, such as an invoice number, contract reference or salary month. It is limited to foO
:71A:A three letter code stating who pays the transfer charges. OUR means the ordering customer pays all charges, BEN means the beneficiary pays all charges, and SHAM
Meridian Bank London sends an MT103, reference MER1035521, for USD 25,000 value 5 November 2024 to Harbour Bank Singapore to pay Bright Logistics for invoice INV-1187. This is a pre-migration example, from before coexistence ended on 22 November 2025. Field :71A: is SHA, the beneficiary account is given in :59a:, and the payment settles on the value date.

Valid example from the message catalogue. Scheme rules: MT103 is a SWIFT MT (FIN) message, not a base ISO 20022 message: there is no single global scheme rulebook, and each bank and market practice sets its own format limits and cut-off times on top of the

0:00 / 3:38 Step 1 of 5

How 52a and 57a Change Across the Serial Chain

MT103 Optional Fields Deep Dive, Lesson 4 of 7, Narration 3:38, D04 Messaging and standards

MT103

What you will learn

Your objective. By the end of this lesson, you will be able to explain 52a and 57a change across the serial chain. In the serial method, each bank in the chain sends a fresh MT103 to the next bank, deducts its own charge if the charge option allows it, and forwards the remaining amount.

Why it matters. Field 50a, the ordering customer, also stays the same, because the customer who ordered the payment does not change as the money moves.

Chapter objective: Learner explains the optional MT103 fields 52a, 57a, 53B, 70 and 71G, and shows how each one changes routing, charges and remittance information. Learner uses real examples with amounts, banks and message names to show how the topic works in practice.

Key learning points

  • Serial method
  • Field 52a
  • Field 57a stays constant
  • Worked chain
  • Practical lesson for operations teams

Key terms

MT103: A SWIFT message that carries a single customer credit transfer instruction from one bank to another. It names the ordering customer, the beneficiary, the amount, the currency and the value date.

SWIFT MT message viewer showing How 52a and 57a Change Across the Serial Chain.

Practise this lesson

Exercise

Route the payment described in this lesson and justify the route.

Use the routing rules, the correspondent chain and the charges in this lesson.

  1. What to do. Name each bank in the chain, the message used on each leg, and the charges deducted at each step.

Correct result. The route follows the correspondent chain from the debtor agent to the creditor agent, with each intermediary deducting its charge and passing the remainder on. The message on each leg carries the information the next bank needs.

Why. Routing is a business decision with a cost. The wrong route is slower, more expensive, or fails.

Check your understanding

Practice question

Which of the following best describes 52a and 57a change across the serial chain?

Takeaway and next step

What to remember

A payment of 95,000 euros from Hamburg to Tokyo that lost its field 52a at the second bank took four days to investigate, because the Tokyo bank could not prove the origin to its compliance team.

Open the message type from this lesson and inspect its fields, then find the field that carries the amount.

Open the ISO 20022 Message Explorer →

Builds on "Field 57a Account With Institution: When and Why It Appears".

Transcript and full text

Show transcript

In the serial method, each bank in the chain sends a fresh MT103 to the next bank, deducts its own charge if the charge option allows it, and forwards the remaining amount. The first bank sends to the second, the second sends to the third, and the third credits the beneficiary. Field 20, the transaction reference, normally stays the same across the chain so every bank can link the legs together, while field 32A changes because the amount falls after each deduction. Field 50a, the ordering customer, also stays the same, because the customer who ordered the payment does not change as the money moves. Field 52a stays constant in meaning but changes in presence across the chain. On the first leg, if the sender is itself the ordering institution, field 52a is absent because the sender and the ordering institution are the same bank. On the second leg, the sender is an intermediary bank that did not take the original instruction, so field 52a must appear and must name the original ordering institution. On the third leg, field 52a still names that same original institution. The value does not change, but its presence does, and that presence tells each receiver that the sender is forwarding a payment ordered by someone else. Field 57a also stays constant in meaning but changes in presence in the opposite direction. On the first and second legs, field 57a names the final beneficiary bank, because the receiver of each early leg is not the bank that holds the beneficiary account. On the final leg, the receiver is the beneficiary bank itself, so field 57a disappears. The sender of the final leg knows that the receiver can credit the beneficiary directly, so naming the receiver again in field 57a would be redundant. A chain that keeps field 57a on the final leg is not invalid in every case, but it is sloppy and can confuse the receiving operations team. A worked chain makes the pattern concrete. BNP Paribas in Paris orders a payment of 367,574.90 dollars for its customer and sends the first MT103 to Wells Fargo in New York. BNP Paribas is the sender and the ordering institution, so field 52a is absent, and Banco Santander in Madrid is the account with institution, so field 57A reads BSCHESMM. Wells Fargo then sends the second MT103 to Bank of New York Mellon. Wells Fargo is now the sender, so field 52A appears with BNPAFRPP, and field 57A still reads BSCHESMM. Bank of New York Mellon then sends the third MT103 to Santander, where field 52A still reads BNPAFRPP and field 57a is gone. The practical lesson for operations teams is to check both fields on every leg before release. If field 52a is missing on a second leg, the next bank cannot see the true origin and may screen the wrong party. If field 57a is missing on an early leg, the receiver may not know where to forward the payment and may hold it. If field 57a is present on the final leg, the receiver should still credit the beneficiary, but it should query the sender to correct the practice. A payment of 95,000 euros from Hamburg to Tokyo that lost its field 52a at the second bank took four days to investigate, because the Tokyo bank could not prove the origin to its compliance team. Worked example with real numbers: the USD 367,574.90 payment from BNP Paribas Paris to Banco Santander Madrid travels as three MT103s, and field 56a and field 57a change at each leg. On the first leg, Paris to Wells Fargo, field 56A is Wells Fargo and field 57A is Bank of New York Mellon. On the second leg, Wells Fargo to Bank of New York Mellon, field 56A is no longer needed, because Wells Fargo is now the sender, and field 57A becomes the Madrid bank, because Bank of New York Mellon must forward to Madrid. On the third leg, Bank of New York Mellon to Madrid, both 56A and 57A disappear, because the payment has reached the beneficiary bank, and no further forwarding is needed. Source: SWIFT MT103 format specifications; Paiementor serial analysis. Failure and recovery: the chain fails when a bank forwards the payment without recalculating the fields, so the next bank receives a 56A naming a bank that has already been passed, and the payment loops back, or is held for investigation. The recovery is to stop the payment, recalculate the chain from the original instruction, and resend it with the correct fields for the remaining legs, but the recovery takes days, and the beneficiary is paid late. A bank that forwards MT103s without recalculating 52a, 56a and 57a will create loops, and the BA must require the recalculation to be tested with a three-leg worked example, where each leg is checked separately, because a test that checks only the first leg will miss the loop. For a business analyst, product owner or subject matter expert, the serial chain requirement must name the recalculation rule for each field at each hop, with a worked example showing the fields on each leg, and must state what happens when a field is wrong: the payment is held, returned or looped, and the recovery is a recalculation and a resend. The ISO 20022 pacs.008 carries the same chain in its agent fields, and the requirement must map each MT field to its pacs.008 equivalent, so the chain survives migration. A chain that is correct in MT but wrong in MX is a migration failure, and the test must cover all three legs.

In the serial method, each bank in the chain sends a fresh MT103 to the next bank, deducts its own charge if the charge option allows it, and forwards the remaining amount. The first bank sends to the second, the second sends to the third, and the third credits the beneficiary. Field 20, the transaction reference, normally stays the same across the chain so every bank can link the legs together, while field 32A changes because the amount falls after each deduction. Field 50a, the ordering customer, also stays the same, because the customer who ordered the payment does not change as the money moves.

Field 52a stays constant in meaning but changes in presence across the chain. On the first leg, if the sender is itself the ordering institution, field 52a is absent because the sender and the ordering institution are the same bank. On the second leg, the sender is an intermediary bank that did not take the original instruction, so field 52a must appear and must name the original ordering institution. On the third leg, field 52a still names that same original institution. The value does not change, but its presence does, and that presence tells each receiver that the sender is forwarding a payment ordered by someone else.

Field 57a also stays constant in meaning but changes in presence in the opposite direction. On the first and second legs, field 57a names the final beneficiary bank, because the receiver of each early leg is not the bank that holds the beneficiary account. On the final leg, the receiver is the beneficiary bank itself, so field 57a disappears. The sender of the final leg knows that the receiver can credit the beneficiary directly, so naming the receiver again in field 57a would be redundant. A chain that keeps field 57a on the final leg is not invalid in every case, but it is sloppy and can confuse the receiving operations team.

A worked chain makes the pattern concrete. BNP Paribas in Paris orders a payment of 367,574.90 dollars for its customer and sends the first MT103 to Wells Fargo in New York. BNP Paribas is the sender and the ordering institution, so field 52a is absent, and Banco Santander in Madrid is the account with institution, so field 57A reads BSCHESMM. Wells Fargo then sends the second MT103 to Bank of New York Mellon. Wells Fargo is now the sender, so field 52A appears with BNPAFRPP, and field 57A still reads BSCHESMM. Bank of New York Mellon then sends the third MT103 to Santander, where field 52A still reads BNPAFRPP and field 57a is gone.

The practical lesson for operations teams is to check both fields on every leg before release. If field 52a is missing on a second leg, the next bank cannot see the true origin and may screen the wrong party. If field 57a is missing on an early leg, the receiver may not know where to forward the payment and may hold it. If field 57a is present on the final leg, the receiver should still credit the beneficiary, but it should query the sender to correct the practice. A payment of 95,000 euros from Hamburg to Tokyo that lost its field 52a at the second bank took four days to investigate, because the Tokyo bank could not prove the origin to its compliance team.

Worked example with real numbers: the USD 367,574.90 payment from BNP Paribas Paris to Banco Santander Madrid travels as three MT103s, and field 56a and field 57a change at each leg. On the first leg, Paris to Wells Fargo, field 56A is Wells Fargo and field 57A is Bank of New York Mellon. On the second leg, Wells Fargo to Bank of New York Mellon, field 56A is no longer needed, because Wells Fargo is now the sender, and field 57A becomes the Madrid bank, because Bank of New York Mellon must forward to Madrid. On the third leg, Bank of New York Mellon to Madrid, both 56A and 57A disappear, because the payment has reached the beneficiary bank, and no further forwarding is needed. Source: SWIFT MT103 format specifications; Paiementor serial analysis.

Failure and recovery: the chain fails when a bank forwards the payment without recalculating the fields, so the next bank receives a 56A naming a bank that has already been passed, and the payment loops back, or is held for investigation. The recovery is to stop the payment, recalculate the chain from the original instruction, and resend it with the correct fields for the remaining legs, but the recovery takes days, and the beneficiary is paid late. A bank that forwards MT103s without recalculating 52a, 56a and 57a will create loops, and the BA must require the recalculation to be tested with a three-leg worked example, where each leg is checked separately, because a test that checks only the first leg will miss the loop.

For a business analyst, product owner or subject matter expert, the serial chain requirement must name the recalculation rule for each field at each hop, with a worked example showing the fields on each leg, and must state what happens when a field is wrong: the payment is held, returned or looped, and the recovery is a recalculation and a resend. The ISO 20022 pacs.008 carries the same chain in its agent fields, and the requirement must map each MT field to its pacs.008 equivalent, so the chain survives migration. A chain that is correct in MT but wrong in MX is a migration failure, and the test must cover all three legs.

Full lesson text (all scenes)

Completing a lesson updates your progress dashboard on the homepage.

Scene timestamps are estimated by allocating the narration text proportionally across the real audio length. The audio playback position is the source of truth: pause freezes the visual, seeking restores the correct scene, replay restarts the scene animation.